    Project Background
    The new energy vehicle manufacturing base features four major process workshops—stamping, welding, painting, and final assembly—and boasts a high and complex electrical load profile.

    Customer needs

    Meeting the impact load requirements of large-scale equipment

    Requires extremely high voltage stability

    Harmonics need to be addressed to ensure equipment operation.

    High-reliability continuous production required

    Product Solution

    Providing industrial-grade power distribution systems

    Configure a Dynamic Reactive Power Compensation Device

    Deploying active filters to mitigate harmonics

    Establish an intelligent power distribution monitoring system

    Implementation results

    Voltage compliance rate improved to 99.9%.

    Production line equipment failure rate reduced by 30%

    Power factor stabilized above 0.95